Solid Waste Downtown Collections Public Meeting on April 16

Clayton Street Improvement Project Update - Aug. 17, 2018

Online Streetscape Visual Preference Survey Ends Sun., Aug. 19


Thanks to those who came by the two public meetings to look over the visual preference survey for the Clayton Street Improvements streetscape and provide input on options.

An online version of the visual preference survey is still available through Sunday, August 19 at accgov.com/clayton.

Visual Preference Survey

Project Schedule Remains Ahead of Schedule, Moving to North Side of Block Two


Crews are scheduled to finish up the pre-dig on the South Side of Block Two (College Ave. to N. Jackson St.) once they complete the southwest corner landscape area of North Jackson Street and East Clayton Street, which is expected on Monday, August 20. 

On the same day (August 20), they will also begin the pre-dig work on the North Side of Block Two, approximately one week ahead of the revised schedule and three weeks ahead of the original schedule. See the map below - they have already completed the crossing of Clayton Street noted on the map.

Currently, the North Side of Block Two is expected to undergo work from August 20-30 (Mon.-Fri. mornings). Once complete, crews will begin pre-dig work on the South Side of Block Three (N. Jackson St. to N. Thomas St.).

Current Clayton Street Pre-Dig Map

Continuing Working through Thursdays


Crews will continue working through Thursdays and then allow for re-paving and repair on Friday mornings to fully open up parking and all lanes on the weekends.

By the end of Thursday afternoons, crews will shrink the fencing to only those areas needed to be repaired and expect to have asphalt work completed by late Friday morning to fully open the parking and roadways for the weekend.

Clayton Street Improvements - Block Two

Clayton Street Improvements Project Timeline 


General tentative project schedule:

  • Pre-Dig Phase (for Stormwater System) - June 18 - Nov. 1, 2018
    • Block 1 (S. Lumpkin to College) - June 18 - Aug. 3 (complete)
      • South side - June 18 - July 19 (complete)
      • North side - July 16 - Aug. 3 (complete)
    • Block 2 (College to N. Jackson) - Aug. 6-30
      • South side - Aug. 6-20 (current)
      • North side - Aug. 20-30 (current)
    • Block 3 (N. Jackson to Thomas) - Oct. 8 - Nov. 1 (to be updated as work moves closer)
  • Private Utility Relocations - August 2018 - April 2019
  • Stormwater System Installation by Athens-Clarke County - January 2019 - March 2020 (break from August 2019 - January 2020)
  • Streetscape Installation by Private Contractor - April 2019 - August 2020 (break from November 2019 - April 2020)

Current Phase: Pre-Dig for Stormwater System


The Pre-Dig phase for the Clayton Street Improvements started Monday, June 18 when crews started digging trenches for the future stormwater system. Actual installation of the stormwater system will begin in January 2019.

The goal is to resolve any issues such as conflicts with other underground items earlier in the process so that the actual installation of the system goes quicker.

  • Work started near N. Lumpkin Street on June 18 and will move block-by-block to Thomas Street until November 2018
  • Crews will work one side of a block at a time (south side and then the north side)
  • Construction work will take place Monday - Thursday from 6:00 a.m. - 4:30 p.m. (except for any holidays) and Friday mornings from 6:00-~11:00 a.m. By Thursday evenings, the fenced area will shrink to enclose only the needed areas for repair. Repaving and repair will take place on Friday mornings to reopen all parking spaces and lanes.*
  • Work will take place in a rolling work zone of up to approximately 200' at a time and require lane closures and parking space closures of 10-15 spaces at a time.

As work is completed, areas will be re-opened as soon as feasible. All lanes and spaces are expected to be re-opened at the end of each pre-dig work week by Friday mornings.*

Detailed block-by-block/side of street maps and more information are available at www.accgov.com/clayton. Additionally, staff continue to visit businesses in the affected areas to provide maps and answer questions about the project.

* - If weather conditions prevent placing asphalt, closures and work days/times may be extended before an area can re-open.

Additional information and upcoming dates that relate to the Clayton Street Area project will continue to be sent through this listserve and linked at www.accgov.com/clayton.