26 - 3 Bridge Improvements

Project Details

  • Sub Project 1: MLK, Jr Parkway Culvert Replacement
    • This project is complete.
  • Sub-Project 2: FY18 Bridge Improvements 
    • Project Details: Phase I includes the structural repair & maintenance of 6 bridges as recommended by a biannual inspection conducted by GDOT. On May 1st, 2018, M&C voted to award the contract to Sun Coast Restoration & Waterproofing, LLC. Construction is in progress.
    • Update: A notice to proceed was issued to Sun Coast Restoration & Waterproofing, LLC on June 1, 2018. The contractor has completed repair work on Fowler Road Bridge, Cleveland Road Bridge, E. Broad over the N. Oconee River, North Avenue Bridge over the N. Oconee River and Macon Highway over the Middle Oconee River. Consultants are identifying additional repairs needed on 15 other bridges. Phase 2 of this project includes additional bridges to be assessed and repaired with remaining budget and available resources. Staff identified maintenance and repair needs on 4 additional bridges that will be addressed with lane restrictions and lane closures only:
      • Beaver Dam Road over Shoal Creek 
      • Trail Creek Street over Trail Creek 
      • Vine Street over Trail Creek 
      • Chase Street over CSX Railroad

Key Project Statistics

  • Designer: Arcadis
  • Contractor: ER Snell
  • Program Manager: Jacobs Engineering
  • Sponsor: Transportation and Public Works
  • Original SPLOST Budget: $990,014 
  • Total Cost: TBD
  • Completion Date: TBD

*as of 7/15/2019