Sub-Project 1: East Campus Connector

Project Details

Project includes a new pedestrian/bicyclist bridge over the North Oconee River connecting the recently completed greenway segments to the UGA East Campus/River Road area. Current schedule is for the bridge to be substantially complete by fall 2019.  

Project Updates

All aerial sections of concrete decking are substantially complete. Concrete installation on the bridge decking is in progress as are handrails and the ground-level portion of the greenway.

SPLOST 2011 Project Monthly Update

Key Project Statistics

  • Designer: Pond and Company 
  • Contractor: Astra Group, Inc.
  • Program Manger: Jacobs Engineering
  • Sponsor: Leisure Services
  • Original SPLOST Budget: $2,688,207.67
  • Grants or other funding: $440,000
  • Total Cost to date: $2,688,207.67
  • Completion Date: Scheduled for fall 2019

*as of 5/15/2019