Description:  A culvert under Barber Street unexpectedly failed, threatening public safety and requiring the road to be closed to through traffic.

The project includes the replacement of a failed 12"x8" elliptical corrugated metal pipe plate pipe carrying a live stream with a double 10"x8" concrete box culvert with headwalls. A major utility relocation was deemed necessary before the contractor, E.R. Snell, could start on the culvert relocation.

Project Schedule: The project is estimated to be complete March 2019.

Project Updates: Atlanta Gas Light has completed the relocation of their facilities in the project vicinity. The contractor has mobilized to the project site and begun work.

For more project updates, visit the Manager's Snapshot. 