Pavement Maintenance Program

The roadway list for the 2020 Pavement Maintenance Program was approved by Mayor and Commission on March 3, 2020.

The total budget for this year’s work is $6,234,110 and is being funded by General Capital Fund, SPLOST 2011, TSPLOST 2018, GDOT Local Maintenance and Improvement Grant (LMIG) and Public Utilities General Capital Fund.

A total of 44 roadway segments are approved for prevention treatment, totaling approximately 42.08 lane-miles of surface.

A total of 100 roadway segments are approved for rehabilitation, totaling approximately 76.20 lane-miles of surface.

Paving typically takes place between June and October, coinciding with warmer weather.

Road / Lane closings may occur in short duration.

Please visit the Road & Lane Closure page for a complete listing of weekly closings.