Road & Lane Closures

Closure Notes
Red text indicates new closures or revisions made to existing closures this week. All road and lane closures are scheduled pending weather conditions. View the Lane Closure Form to request a lane closure. Email Engineering@accgov.com for more information.

 
 Road Closures
 Barber Street from Chase Street - Maxey Street  August 21 - March 29, 2019  Culvert Replacement  E. R. Snell Contractor
 Baxter Street from Lumpkin Street - Newton Street  May 13 - August 1, 2019  Sewer line replacement  ACC Public Utilities
 Camelot Drive from Camelot Lane - Partridge Lane  February 25 - April 30, 2019  Replacing cross drain pipe  ACC Streets & Drainage
 Gilmer Street from Hawthorne Avenue - Clover Street  February 18 - March 29, 2019  Install storm drain  J W York Homes
 Hull Street from Baxter Street - 250' west of Baxter Street  May 13 - August 1, 2019  Sewer line replacement  ACC Public Utilities
 Hull Street from W. Washington Street - Clayton Street (4pm - 6pm AND 9pm - 11pm) March 28, 2019 and March 30, 2019  Forklift load in for UGA event  Morton Theatre
 Hull Street from W. Washington Street - Clayton Street (10am - 12pm AND 1pm - 3pm) April 10, 2019 and
April 15, 2019
 Forklift load in for play  Morton Theatre
 King Avenue from Cobb Street - Hill Street  March 24 - 25, 2019  Install 2 roof top units for Piedmont Athens Vertical Expansion  Batchelor & Kimball, Inc.
 Meigs Street from N. Chase Street - Franklin Street  March 18 - April 12, 2019  Water main installation   Site Engineering
 McLeroy Drive from Whitehead Road - Gardina Avenue  January 22 - March 29, 2019  Water main installation  Site Engineering
 Millstone Circle  (dam area only)  February 26 - May 31, 2019  Dam repair  Structural Resources, Inc. for ACC
 Morton Avenue from S. Milledge Avenue - Northview  March 11 - 15, 2019  Sewer main  Mike Nelms
 Newton Street from Baxter Street - Waddell Street  April 1 - May 8, 2019  Sewer installation  ACC Public Utilities
 Newton Street from Prince Avenue - Meigs Street  March 25 - 28, 2019  Replace sidewalk and curb  ACC Streets & Drainage
 Oak Grove Road from Jefferson Road - Old Jefferson Road  March 4 - April 10, 2019  Track maintenance  CSX Transportation
 Whitehead Road from Jefferson Road - Old Jefferson Road  March 4 - April 10, 2019  Track maintenance  CSX Transportation
Sidewalk 
 Baxter Street from Lumpkin Street - Newton Street (north side) May 13 - June 8, 2019   Sewer line replacement  ACC Public Utilities
 Broad Street from Newton Street - Lumpkin Street (9:00am - 3:00pm) February 25 - May 1, 2019   Demolition of old wall at Pulaski Street intersection and construction of new wall  GDOT
  Broad Street from Newton Street - Thomas Street
April 2 - July 1, 2019
 
  Drilling of signal pole foundations
  Georgia Department of Transportation
 Childs Street from Prince Avenue - Barrow Street February 4 - April 26, 2019   Intermittent sidewalk closure to allow trucks to enter and leave project site  Barnett Shoals Corporation
 131 E. Clayton Street from 125 - 145 March 4 - 22, 2019   Facade restoration  Tyler Leslie
 King Avenue from Cobb Street - King Avenue  October 15 - April 30, 2019  Vertical addition  DPR Construction
 Lumpkin Street from Wray Street - Rutherford Street  May 13 - July 20, 2019  Sewer line replacement  ACC Public Utilities
 Newton Street from Prince Avenue - Meigs Street  March 25 - 28, 2019  Replace sidewalk & curb  ACC Streets & Drainage
 Prince Avenue from Pulaski Street - Barber Street February 4 - April 26, 2019   Unload equipment on to site  trechel.com
  Prince Avenue from Pulaski Street - Childs Street
 February 11 - April 26, 2019  Construction  trechel.com
 Prince Avenue from Pulaski Street - Childs Street February 4 - April 26, 2019   Intermittent sidewalk closure to allow trucks to enter and leave project site  Barnett Southern Corporation
 Pulaski Street from Prince Avenue - Barrow Street (SB lane to be closed on an as needed basis)  February 11 - April 26, 2019  Construction  Barnett Southern Corporation
 Willow Street from E. Broad Street - Aguar Plaza March 18 - May 11, 2019   Re-roof construction  Dakota Wells
 Lane Closures
 Camelot Drive from Camelot Lane - Partridge Lane
(One lane road.  MUST STOP AT WORK ZONE)
November 29 - April 30, 2019  Road is failing due to pipe failure  ACC Streets & Drainage
 Danielsville Road from 745 Danielsville Road - 86 North Avenue  September 17 - March 31, 2019  Install poles and build a transmission line along the road way  Georgia Power Company
  Lumpkin Street from Wray Street - Rutherford Street
  May 13 - July 20, 2019
 Sewer line replacement
  ACC Public Utilities
 Odd Street from Griffeth Street - First Street  March 1 - 31, 2019  Waterline work and asphalt paving
 RDJE, Inc.
 Prince Avenue @ Finley Street (8:00am - 6:00pm)  March 26 - 29, 2019  Bus stop installation  Structural Resources, Inc.
 Prince Avenue from Pulaski Street - Childs Street (Intermittent)
8:00am - 5:00pm
 February 4 - April 26, 2019  Trucks entering and leaving the 100 Prince project site  Barnett Southern Corporation
 Pulaski Street from Prince Avenue - Barrow Street (SB lane to be closed on a as needed basis)  March 18 - April 29, 2019  Construction activities  Barnett Southern
 S. Milledge Avenue from Baxter Street - Broad Street (Intermittent lane)  March 25 - April 5, 2019  Flower planting in medians  ACC Landscape Management
 S. Milledge Avenue from 2500 S. Milledge Avenue - Whitehall Road  March 18 - June 28, 2019  Construction of round-a-bout  Vertical Earth
 Tremont Parkway from Atlanta Highway - Cul de sac March 4 - 22, 2019  Sanitary sewer tie-in  Vertical Earth Inc.
 Whitehall Road from 1055 - 895
 March 18 - June 28, 2019
 Construction of round-a-bout
  Vertical Earth, Inc.
Lane Restrictions
 Barnett Shoals Road from Jittery Joes - Chick Fil A  March 18 - 22, 2019  Placing span cable  Toby Williams
 Broad Street from Newton Street - Thomas Street  April 2 - July 1, 2019  Drilling of signal pole foundations  Georgia Department of Transportation
 College Avenue from Willow Street - Ware Street March 25 - 29,  2019  Tree work  ACC Landscape Management
  Lumpkin Street from Wray Street - Rutherford Street
  May 13 - July 20, 2019
 Sewer line replacement
 ACC Public Utilities
 North Oconee Street left turn lane/Access Road - Greenway Access - 300' from College Station intersection  March 18 - 22, 2019  Storage area for transport trucks   Astra Group
 Prince Avenue from Pulaski Street - Barber Street  February 4 - April 26, 2019  Unload equipment on site  Trechel.com
 S. Milledge Avenue from 2500 S. Milledge Avenue - Whitehall Road
  March 18 - June 28, 2019
 Construction of round-a-bout
 Vertical Earth, Inc.
 Whitehall Road from 1055 - 895
 March 18 - June 28, 2019
  Construction of round-a-bout
 Vertical Earth, Inc.
Special Events
March for Meals 5K
Hull Street; Dougherty Street; Prince Avenue; Satula Avenue; Boulevard Avenue; Barber Street; Pulaski Street; Hancock Avenue
March 23, 2019 Fundraiser for ACCA's Meals on Wheels on program Athens Community Council
 Firefly Trail 8th Annual Ticket to Ride
Barber Street; Cleveland Avenue; College Avenue; Willow Street; North Avenue; Hickory Street; Broad Street; Arch Street; Peter Street/Olympic Drive; Indian Hills Road; Springvalley Road; Moore's Grove Road; Athens Road; Main Street; Parkview Road
March 23, 2019  Bicycle ride to raise awareness and funds for Firefly Trail from Athens to Union Point  Firefly Trail, Inc. 