Greencrest Dr/East Creek Bend Stormwater Improvements Project

The Greencrest Drive (CE-40) and East Creek Bend Stormwater Improvements Project includes two projects under one construction contract.  

The Greencrest Drive project consists of the installation of a storm drain pipe and associated structures, header curb, headwall construction and Rip Rap installation, roadway milling and overlay, and the construction of a drainage ditch.

The East Creek Bend project includes the removal and replacement of the existing 54" corrugated metal pipe with a 14' x 4' precast bottomless arch culvert.  Work also includes the construction of gabion walls, relocation of an existing waterline and minor asphalt work.

On February 7, 2017, a construction contract was awarded to Georgia Development Partners and construction is scheduled to begin in early April 2017.  The project is scheduled for completion in late September 2017.

For more information, please contact Engineering Division at (706) 613-3440

Was this page helpful for you? Yes No