Project 25: North Oconee Rivers Greenway

Project Description
The North Oconee Rivers Greenway Project project consists of the acquisition of properties and easements on the North Oconee River and development of greenway trails for public use.  Parcels may provide stream buffer, recreational access to the river, and/or Greenway opportunities as outlined in the ACC Greenway Network Plan

Project Details
  • Project Sponsor: Leisure Services
  • Type: Greenways
  • Project Manager: Derek Doster 

Status: August 31, 2012

  • The North Oconee Rivers Greenway project is divided into two separate Greenway trail sub-projects, both of which are partially funded via Federal Grants in addition to SPLOST 2005 funding. The Grants require compliance with the Georgia Department of Transportation (GDOT) procedures and process for all design, environmental review and construction.  
    • Sub-project A, the “Trail Creek Segment,” is the segment of the Greenway from East Broad Street to East Athens Community Park.
      • The Mayor and Commission approved the preliminary construction plans on May 6, 2008.
      • On February 3, 2010, the Georgia Department of Transportation (GDOT) approved the right of way plans and issued a notice to proceed with right of way acquisition. Right-of-way acquisition and final construction plans are in progress and final negotiation of all necessary property rights is anticipated in November 2012. The construction phase is planned for the spring of 2013.

    • Sub-project B, the “North Oconee River Segment,” is the segment of the Greenway from Dudley Park to College Station Road.
      • The Mayor and Commission approved the Preliminary Construction Plans on May 5, 2009.  Special studies and environmental documentation work in accordance with the GDOT process was initiated and on October 7, 2010. GDOT requested additional field studies and information in regard to the archeology studies. Processing of this additional information and final environmental assessments are in progress. Final Plans are scheduled for completion by Dec 2012 and construction start in spring 2013.
  • Final compliance with the GDOT process in progress; construction activities anticipated in the spring of 2013.

 

Budget

Fiscal Period

Amount

FY 2006 (Tier 1)

$250,000

FY 2007 (Tier 2)

$567,376

FY 2008 (Tier 3)

$2,839,377

Total for this project:

$3,656,753