Project 6: East Athens Community Park (now Trail Creek Park) - Phase 2

Project Description
The East Athens Community Park (now Trail Creek Park) – Phase II Project was divided into two separate sub-projects, Phase II-A and Phase II-B:

Phase II-A sub-project was the Peter Street entrance roadway and bridge. This sub-project included a new intersection between Peter Street and a connecting park entrance roadway section connecting Peter Street to the existing Park road system. A 160 foot long bridge structure was utilized to span Trail Creek and the entire roadway includes an eight foot wide pedestrian sidewalk section and all appropriate roadway appurtenances.

The Phase II-B sub-project is the construction and installation of new park elements inside the park including additional lighting to the sports fields, additional walking trails, new playground areas, a 100 person splash pad area, picnic areas and facilities, an interactive basketball area, additional restroom facilities and new parking areas.

Project Details

  • Project Sponsor: Leisure Services
  • Type: Parks and Recreation
  • Project Manager: Derek Doster 

Status: August 31, 2012

The Phase II-A sub-project, Peter Street entrance roadway and bridge, was completed in July 2010 and the roadway entrance opened for public use. 

A Notice to Proceed with Construction was issued on May 29, 2012 for the Phase II-B sub-project work. Completion of the Phase II-B construction is scheduled for December 2012.


Fiscal Period


FY 2006 (Tier 1)


FY 2007 (Tier 2)


FY 2008 (Tier 3)


Total for this project: