Description

The project upgraded and improved major transit stops along the Athens Transit Bus System routes. The improvements for these transit stops were evaluated for their specific needs. Improvements include:
  • Bicycle racks
  • Bus pull-off to allow traffic to have a clear lane while the bus is loading and unloading
  • Installation of proper signage, a paved pad, benches, and a covered shelter
  • Landscaping
  • Route information

Budget


  • Original SPLOST Budget: $1,167,792
  • Budget Amendments: -$167,721
  • Adjusted SPLOST Budget: $1,000,071
  • Amount Expended: $999,738