Project 11: Airport Land Acquisition

Description
The project acquired approximately 40 acres of land necessary to construct the future Airport Commercial Terminal Facility, with an entrance from U.S. Highway 78.

Budget
  • Original SPLOST Budget: $1,067,822 
  • Budget Amendments: -$38,295 
  • Adjusted SPLOST Budget: $1,029,527 
  • Amount Expended: $1,029,525