Project 6: General Intersection Improvements

Project Description


This project was designed to improve intersections throughout Athens where increased traffic flow had caused congestion during peak periods. The project is complete.

Budget


  • Original SPLOST Budget: $1,200,000
  • Budget Amendments: $722,000
  • Adjusted SPLOST Budget: $1,922,000
  • Amount Expended: $1,922,000