 Road Closures
 3065 Atlanta Highway from Ultimate Drive - Driveway into Target  March 20 - 24, 2017  Overlash FOC Across Atlanta Highway  AT&T
 Cobb Street from N. Milledge Avenue - Prince Avenue March 11 - 24, 2017 Install New Water Line RDJE, Inc.
 Meigs Street March 24, 2017  Milling and Paving  RDJE, Inc.
 N. Harris Street from Cobb Street - Prince Avenue  March 11 - 24, 2017
 Install New Water Line
 RDJE, Inc.
 Summerbrook Circle from Summerbrook Drive (Bldg. 17) - Hawthorne Avenue Ext. (Bldg. 3)  March 6 - May 6, 2017  Construction Traffic  Walton Construction Services
 Waddell Street  March 24, 2017
 Milling and Paving
 RDJE, Inc.
Sidewalk 
  College Station Road from Research Drive - Barrett Shoals Road
  October 6, 2016 - March 31, 2017
 Sidewalk Removal/Road Widening
  Vertical Earth
 S. Hull Street from 220 - 240
  October 31 - December  15, 2017
 Water, Storm, and Sanitary Sewer Tap
 Andy Strange Grading
 S. Hull Street from Correll Hall - Baxter Street  January 12 - May 31, 2017  Construction of Business Learning Community Phase 2  Turner Construction Company
 Washington Street from 115 E. Washington Street - 155 E. Washington Street  February 27 - March 25, 2017  Tap Water Main and Extend Fire Protection Water to New Civic Hall Sprinkler System  Kevin Price Construction
 W. Washington Street from N. Lumpkin Street - Pulaski Street  February 20 - March 20, 2017  Replace the Water Line  ACC Public Utilities
 ​Lane Closures
 Ashmore Drive March 6 -18, 2017  Chip Seal, Asphalt Patching, Paving  Pittman Construction
 Barnett Shoals Road at Forest Road  March 8 - 22, 2017  Install Tie-In to Existing Waterline  RDJE, Inc.
 Barnett Shoals Road at Forest Road
 March 14 - 22, 2017  Connect Existing Waterline in Roadway   RDJE, Inc.
 Belvoir Heights   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Benjamin Drive  March 6 -18, 2017
 Chip Seal, Asphalt Patching, Paving
 Pittman Construction
 Best Drive   February 20 - March 31, 2017
  Facilate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Blueberry Hills  March 6 -18, 2017
 Chip Seal, Asphalt Patching, Paving
 Pittman Construction
 Broad Acres Court   February 20 - March 31, 2017
  Facilate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Burkland Drive  March 6 -18, 2017
 Chip Seal, Asphalt Patching, Paving
 Pittman Construction
 Camellia Drive  March 6 -18, 2017
 Chip Seal, Asphalt Patching, Paving
 Pittman Construction
 Clover Street   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Cobb Street   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 College Station Road from Research Drive - Barnett Shoals Road
 October 6, 2016 - March 31, 2017
  Sidewalk Removal/Road Widening
 Vertical Earth
 Colima Drive  March 6 -18, 2017
 Chip Seal, Asphalt Patching, Paving
 Pittman Construction
 Crestview Circle  March 15 - 31, 2017   Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation

 Compliance Envirosystems
 Edwards Circle   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Edwards Drive   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Fernwood Court  March 6 -18, 2017
 Chip Seal, Asphalt Patching, Paving
 Pittman Construction
 Foundry Street from Broad Street - E. Dougherty Street  March 23, 2017  Pedestrian Traffic  The Classic Center
 Fowler Drive  March 6 -18, 2017
 Chip Seal, Asphalt Patching, Paving
 Pittman Construction
 Gardenia Drive  March 6 -18, 2017
 Chip Seal, Asphalt Patching, Paving
 Pittman Construction
 Glenhaven Avenue   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Hancock Avenue   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Hart Avenue   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Hemlock Way  March 6 -18, 2017
 Chip Seal, Asphalt Patching, Paving
 Pittman Construction
 Hill Street   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Hillcrest Avenue   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Hodgson Drive   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Holman Avenue   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Indale Avenue  March 15 - 31, 2017    Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Jennings Mill Road from Dowdy Road - Wickersham Road
 February 27 - March 20, 2017
 Change Out Poles
 David Fitzpatrick
 Jones Drive  March 6 -18, 2017
 Chip Seal, Asphalt Patching, Paving
 Pittman Construction
 Kenwood Drive  March 6 -18, 2017
 Chip Seal, Asphalt Patching, Paving
 Pittman Construction
 King Avenue   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Loblolly Drive  March 6 -18, 2017
 Chip Seal, Asphalt Patching, Paving
 Pittman Construction
 Matthews Avenue   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Millard Avenue   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Normal Avenue   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 N. Rocksprings Street   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 N. Thomas Street from Hancock Avenue - E. Dougherty Street  February 21 - April 17, 2017  Athens Hyatt Place Construction  R W Allen 
 Oakbend Court  March 6 -18, 2017
 Chip Seal, Asphalt Patching, Paving
 Pittman Construction
 Oglethorpe Avenue  February 20 - March 31, 2017  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation  Compliance Envirosystems
 Oglethorpe Terrace   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Old Jefferson Road  March 6 -18, 2017
 Chip Seal, Asphalt Patching, Paving
 Pittman Construction
 Old W. Broad Street   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Orchard Creek Drive  March 6 -18, 2017
 Chip Seal, Asphalt Patching, Paving
 Pittman Construction
 Pine Needle Road   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Prince Avenue   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Reese Street   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Robinhood Court  March 6 -18, 2017
 Chip Seal, Asphalt Patching, Paving
 Pittman Construction
 Smithonia Road  March 6 -18, 2017
 Chip Seal, Asphalt Patching, Paving
 Pittman Construction
 S. Harris Street  - Waddell Street
 February 13 - March 24, 2017   Install Waterline on Shoulder of Road  RDJE, Inc.
 S. Lumpkin Street from W. Lake Drive - Hope Avenue  March 20 - 24, 2017  Install Water Tap  ACC Meter Management
 S Milledge Ave - Waddell Street  February 13 - March 31, 2017
 Install Waterline on Shoulder of Road
 RDJE, Inc.
 Stonehenge Place  March 6 -18, 2017
 Chip Seal, Asphalt Patching, Paving
 Pittman Construction
 Sunset Drive   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Sunset Terrace   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Talmadge Drive   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 The Plaza   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Thomas Street from E. Broad Street - Washington Street  March 15, 2017  Manhole Access  AT&T
 Thomas Street between Hancock Avenue - E. Dougherty Street
 February 24 - April 17, 2017
 Delivery of Materials
 R W Allen
 Timothy Court  March 6 -18, 2017
 Chip Seal, Asphalt Patching, Paving
 Pittman Construction
 Washington Street from 115 E. Washington Street - 155 E. Washington Street
  February 27 - March 25, 2017
 Tap Water Main and Extend Fire Protection Water to New Civic Hall Sprinkler System
 Kevin Price Construction
 Washington Street from N. Lumpkin Street - College Avenue  March 14 - 21, 2017  Repair Pot Hole  ACC Streets & Drainage
 Waverly Court   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 West Lake Drive  March 6 -18, 2017
 Chip Seal, Asphalt Patching, Paving
 Pittman Construction
 Westover Drive   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 W. Washington Street - North Lane from Lumpkin Street - Hull Street (6:00am - 2:00pm)  March 23, 2017  Parking School Buses  Morton Theatre
 W. Washington Street from N. Lumpkin Street - Pulaski Street
 February 20 - March 20, 2017
  Replace the Water Line
  ACC Public Utilities
 Willow Run   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Willow Street  March 6 -18, 2017
 Chip Seal, Asphalt Patching, Paving
 Pittman Construction
 Windsor Court   February 20 - March 31, 2017
  Facillate Equipment Access to Municipal Sewer Lines to Conduct Sanitary Sewer Evaluation
 Compliance Envirosystems
 Woody Drive  March 6 -18, 2017
 Chip Seal, Asphalt Patching, Paving
 Pittman Construction
Lane Restrictions
 Barber Street from Barrow Street - Atlanta Avenue  March 6 - May 6, 2017  Splice Aerial Fiber Optic Cable  AT&T
 Boulevard Avenue from Wynburn Avenue - Barber Street  March 6 - May 6, 2017  Splice Aerial Fiber Optic Cable  AT&T
 E. Broad Street from Hickory Street - Hickory Street (Intermittent Lanes)  March 6 - April 7, 2017  Facilitate Installation of Traffic Signal   R.J. Haynie & Associates
 MLK Parkway from Ruth Drive - Strickland Avenue (Intermittent Lanes)  March 6 - May 8, 2017  Loading/Unloading Equipment and Materials  E. R. Snell
 Old Commerce Road from N. Bluff Road - Old Creek Road (Intermittent Lanes)  March 14 - 31, 2017  Install New Waterline  RDJE, Inc.
 Prince Avenue/Oglethorpe    March 20 - 24, 2017  Fiber Optic Splicing  AT&T
 Riverbend Parkway from Woodstone Drive - Fernbanks Court (Intermitten Lanes)  March 15 - 24, 2017  Emergency Storm Drain Repair  ACC Streets & Drainage
W. Washington Street from N. Lumpkin Street - Pulaski Street
February 20 - March 20, 2017

 Replace the Water Line

 ACC Public Utilities