Road & Lane Closures

Closure Notes
Red text indicates new closures or revisions made to existing closures this week. All road and lane closures are scheduled pending weather conditions. View the Lane Closure Form to request a lane closure. Email Engineering@athensclarkecounty.com for more information.
 

 Road Closures

Foundry Street from Level 2 Classic Center Parking Deck Entrance - Strong Street  October 9, 2015  Chase Rice Concert in 440 Foundry Pavilion  The Classic Center

No Parking





 Sidewalk

 Clayton Street  September 8 - October 1, 2015  Sidewalk Closure for Demolition  R W Allen
 E. Clayton Street from 175 - 195 August 31 - September 3, 2015 Install Communicating Vaults  Charter Communications
 170 Milledge Avenue from Broad Street - Hancock Avenue  June 17 - September 18, 2015  Building Construction/Side Repair  Optum Construction/Best Western

Lane Closures




 3220 Barnett Shoals Road  September 5 - 19, 2015  Construction, Maintenance and Operation of Electrical System
 Georgia Power & Approved Contractors
 Baxter Street  August 31 - September 11, 2015  Crack/Chip Sealing and
Paving
  Pittman Construction
 960 Belmont Road  September 5 - 19, 2015  Construction, Maintenance and Operation of Electrical System
 Georgia Power & Approved Contractors
 Bishop Drive  August 31 - September 11, 2015
 Crack/Chip Sealing
  Pittman Construction
 Civitan Club Drive  September 5 - 19, 2015  Construction, Maintenance and Operation of Electrical System
Georgia Power & Approved Contractors
 Coile Drive from Mitchell Bridge Road - 800 feet down Coile Road (Intermittent Lanes)  November 17 - September 30, 2015
 Install Storm Drain Pipe  Strickland & Sons Pipeline
 130 Deerwwod Court  September 5 - 19, 2015  Construction, Maintenance and Operation of Electrical System
 Georgia Power & Approved Contractors
 S. Finley Street
 August 31 - September 11, 2015 Crack/Chip Sealing and
Paving
 Pittman Construction
 190 Georgia Avenue  September 5 - 19, 2015  Construction, Maintenance and Operation of Electrical System
 Georgia Power & Approved Contractors
 Greystone Terrace   August 31 - September 11, 2015
 Crack/Chip Sealing/Surface Treatment
  Pittman Construction
 Harwood Court   August 31 - September 11, 2015
 Crack/Chip Sealing
  Pittman Construction
 4875 Old Lexington Road  September 5 - 19, 2015 Construction, Maintenance and Operation of Electrical System

 Georgia Power & Approved Contractors
 5555 Old Lexington Road  September 5 - 19, 2015  Construction, Maintenance and Operation of Electrical System  Georgia Power & Approved Contractors
 285 Old Will Hunter Road  September 5 - 19, 2015  Construction, Maintenance and Operation of Electrical System
 Georgia Power & Approved Contractors
 Lullwater Road  August 31 - September 11, 2015
 Crack/Chip Sealing
  Pittman Construction
 Maple Circle   August 31 - September 11, 2015
 Crack/Chip Sealing
  Pittman Construction
 Maple Wood Court
 August 31 - September 30, 2015  Patching  Pittman Construction
 100 Milledge Heights  September 5 - 19, 2015  Construction, Maintenance and Operation of Electrical System
 Georgia Power & Approved Contractors
 Mitchell Bridge Road from Coile Drive - Preserve Drive (Intermittent Lane Restriction)  February 2 - September 4, 2015  Road Construction  Strickland & Sons Pipeline
 690 Morton Road  September 5 - 19, 2015  Construction, Maintenance and Operation of Electrical System
 Georgia Power & Approved Contractors
 2005 Morton Road  September 5 - 19, 2015  Construction, Maintenance and Operation of Electrical System  Georgia Power & Approved Contractors
 Morton Road at Millstone Court  September 5 - 19, 2015  Construction, Maintenance and Operation of Electrical System
 Georgia Power & Approved Contractors
 Morton Road
 August 31 - September 11, 2015  Crack/Chip Sealing and
Paving
 Pittman Construction
 Oak Street from S. Poplar Street - S. Poplar Street  September 8 - 9, 2015  Manhole Access  AT&T
 Oconee Street from Grove Street - Grove Street  September 8 - 9, 2015  Manhole Access  AT&T
 Paris Street August 31 - September 11, 2015  Crack/Chip Sealing  Pittman Construction
 Pinecrest Drive August 31 - September 11, 2015
 Crack/Chip Sealing  Pittman Construction
 314 Pine Valley Road  September 5 - 19, 2015  Construction, Maintenance and Operation of Electrical System
 Georgia Power & Approved Contractors
 Springdale Street
 August 31 - September 11, 2015  Patching  Pittman Construction
 Tallassee Road from 600' West of Whitehead Road - 600' East of Whitehead Road  September 1 - 30, 2015  Construction, Maintenance and Operation of Electrical System  Strickland & Sons Pipeline
 Third Street
 August 31 - September 11, 2015  Crack/Chip Sealing and
Paving
 Pittman Construction
 184 Vine Street  September 5 - 19, 2015  Construction, Maintenance and Operation of Electrical System
 Georgia Power & Approved Contractors
 Waddell Street August 31 - September 11, 2015
 Crack/Chip Sealing,   Pittman Construction
 W. Broad Street from N. Lumpkin Street - N. Hull Street  September 9 - 11, 2015  Underground Fiber Installation  AT&T
 West Lake Court August 31 - September 11, 2015  Crack/Chip Sealing  Pittman Construction
 Wray Street
 August 31 - September 11, 2015  Crack/Chip Sealing and
Paving
 Pittman Construction
 Tallassee Road from 600 feet West of Whitehead Road - 600 East of Whitehead Road (Intermittent Lane Restriction)  October 27 - September 30, 2015
 Road Construction  Strickland & Sons Pipeline
 Yonah Avenue from Buena Vista Avenue - Satula Avenue  September 8 - October 9, 2015  Install New Water & Sewer Lines  ACC Water & Sewer

Lane Restrictions

 Buddy Christian Road   August 1 - October 1, 2015  Trucks Crossing Road Hauling Dirt  G. P.'s Enterprise
 Tallassee Road from 600 feet West of Whitehead Road - 600 East of Whitehead Road (Intermittent Lanes)  October 27, 2014 - September 4, 2015
 Road Construction  Strickland & Sons Pipeline
 Special Events